Industrial Railways Toronto East
Canadian National Railway
8950 Keele Street, Vaughan
​
View this project slide deck from start to finish -
mouse-over each picture for description or click to stop and view
This project consisted of the design-build construction of an autoport depot at the CN Rail’s McMillan yard. The work completed included the design of structures, erection of the pre-engineered building and an office building/autoport complete with necessary electrical, plumbing, HVAC, partitions, roofing, fixtures and finishes, erection of a guardhouse and security gate, construction of full sized tractor trailer scales, approach ramps, scale house and traffic lights complete, and construction of necessary concrete pads, ramps, curbs and sidewalks.
Over the course of the project, as the needs of the client changed, DeMan worked with both CN, as well as AECOM, the project management company, to ensure that the requests were met and that the over schedule of the project was maintained.
Autoport depot at the CN Rail’s McMillan yard
DeMan worked with both CN, as well as AECOM, the project management company
erection of a guardhouse and security gate
Autoport depot at the CN Rail’s McMillan yard
View this project slide deck from start to finish -
mouse-over each picture for description or click to stop and view
The work completed included the design of structures, erection of the pre-engineered building and an office building/autoport complete with necessary electrical, plumbing, HVAC, partitions, roofing, fixtures and finishes
The work completed included the design of structures, erection of the pre-engineered building and an office building/autoport complete with necessary electrical, plumbing, HVAC, partitions, roofing, fixtures and finishes
The work completed included the design of structures, erection of the pre-engineered building and an office building/autoport complete with necessary electrical, plumbing, HVAC, partitions, roofing, fixtures and finishes
The work completed included the design of structures, erection of the pre-engineered building and an office building/autoport complete with necessary electrical, plumbing, HVAC, partitions, roofing, fixtures and finishes
Tractor trailer scales, approach ramps, scale house and traffic lights complete, and construction of necessary concrete pads, ramps, curbs and sidewalks.
tractor trailer scales, approach ramps, scale house and traffic lights complete, and construction of necessary concrete pads, ramps, curbs and sidewalks.
Tractor trailer scales, approach ramps, scale house and traffic lights complete, and construction of necessary concrete pads, ramps, curbs and sidewalks.
Canadian Pacific Railway
2025 McCowen Road, Scarborough
Over the course of approximately one year, DeMan worked CPR with Toronto Locomotive Reliability Centre project, which included the renovation and retrofitting of two existing shops at their McCowan Yard, over the course of two phases.
​
​In Phase 1, DeMan completed major building renovations as well as a building addition on the existing wheel, Truck Shop and SBI facility. Work completed including building exterior retrofit, major electrical and mechanical work, including a new refuelling station, as well as all required concrete, railway, and finishing work.
At the end phase 1, DeMan begun Phase 2, which centred on the renovation and building addition of the nearby diesel Shop. Work completed was similar, including an exterior retrofit, major concrete, rail, metal, electrical and mechanical work as well as installation and modifications to existing craning systems.
DeMan was also able to make recommendations for specifications alternatives that, while meeting or exceeding the project design requirements, the alternatives saved CPR tens of thousands of dollars over the course of both construction and post-construction maintenance.
The complexity of the work completed was high, and was increased by the tight scheduling required for the projects. Equipment from the second building had to be installed in the first in order to re-open the facility, however, the equipment could not be unavailable for any extended period of time. DeMan worked closely with CPR’s head office and on-site staff as well as CP’s equipment installation contractors to ensure that the project proceeded smoothly and on schedule over the year long period.
View this project slide deck from start to finish -
mouse-over each picture for description or click to stop and view
Over the course of approximately one year, DeMan worked CPR with Toronto Locomotive Reliability Centre project, which included the renovation and retrofitting of two existing shops at their McCowan Yard, over the course of two phases. ​
Work completed was similar, including an exterior retrofit, major concrete, rail, metal, electrical and mechanical work as well as installation and modifications to existing craning systems.
Over the course of approximately one year, DeMan worked CPR with Toronto Locomotive Reliability Centre project, which included the renovation and retrofitting of two existing shops at their McCowan Yard, over the course of two phases. ​
View this project slide deck from start to finish -
mouse-over each picture for description or click to stop and view
Work completed including building exterior retrofit, major electrical and mechanical work, including a new refuelling station, as well as all required concrete, railway, and finishing work.
Work completed including building exterior retrofit, major electrical and mechanical work, including a new refuelling station, as well as all required concrete, railway, and finishing work.
Work completed including building exterior retrofit, major electrical and mechanical work, including a new refuelling station, as well as all required concrete, railway, and finishing work.
View this project slide deck from start to finish -
mouse-over each picture for description or click to stop and view
Work completed included exterior retrofit, major concrete, rail and metal work
Work completed included exterior retrofit, major concrete, rail and metal work
Mechanical work as well as installation and modifications to existing craning systems.
Work completed included exterior retrofit, major concrete, rail and metal work
View this project slide deck from start to finish -
mouse-over each picture for description or click to stop and view
DeMan completed major building renovations as well as a building addition on the existing, Wheel, Truck Shop and SBI facility. Work completed including building exterior retrofit, major electrical and mechanical work, including a new refuelling station, as well as all required concrete, railway, and finishing work
Located in the City of Mississauga at 776 Dundas Street East, DeMan Construction Corp is a design-build and General Contracting company that serves clients throughout Southern Ontario. With over 63 years of experience, DeMan Construction has completed projects for many businesses. Since its inception, the company has been involved in the design and construction of many successful commercial projects. DeMan Construction maintains a full-time staff of approximately 50 commercial construction experts to execute multiple concurrent contracts on time and on budget.